Ashley McGraw Architects, P.C.   MacArthur Elementary School – Project Location: Binghamton – Approximate Square Footage: 130,000 – Start Date: Oct. 15, 2013 – Building Owner: Binghamton City School District – Construction Manager: Hulbert Engineering – Architect: Ashley McGraw Architects – Engineer: Buro Happold – Landscape Architect: Appel Osborne Landscape Architecture     BARTON & LOGUIDICE, D.P.C. […]

Already an Subcriber? Log in

Get Instant Access to This Article

Become a Central New York Business Journal subscriber and get immediate access to all of our subscriber-only content and much more.

Ashley McGraw Architects, P.C.

 

MacArthur Elementary School

- Project Location: Binghamton

- Approximate Square Footage: 130,000

- Start Date: Oct. 15, 2013

- Building Owner: Binghamton City School District

- Construction Manager: Hulbert Engineering

- Architect: Ashley McGraw Architects

- Engineer: Buro Happold

- Landscape Architect: Appel Osborne Landscape Architecture

 

 

BARTON & LOGUIDICE, D.P.C.

 

TOBIE Trail Phase 2/Welcome Center

- Project Location: Town of Webb

- Total Construction Cost: $1.6 million

- Approximate Square Footage: 1.37 miles of trail/1,100-square-foot welcome center

- Building Owner: Town of Webb

- Construction Manager: Barton & Loguidice, D.P.C.

- Architect: Barton & Loguidice, D.P.C.

- Engineer: Barton & Loguidice, D.P.C.

- Landscape Architect: Barton & Loguidice, D.P.C.

- General Contractor: TOBIE Trail: Dow Electric, Inc.; Welcome Center: Richard E. Alexander Co. Inc.

- Primary Subcontractors: Electrical: S.C. Spencer Electric, Inc.; HVAC & plumbing: Superior Plumbing & Heating

- Financing Source: Transportation Enhancement Program administered by NYSDOT

 

Bridgeport Sewer District

- Project Location: Town of Sullivan

- Total Construction Volume: $14 million

- Construction Manager: Barton & Loguidice, D.P.C.

- Engineer: Barton & Loguidice, D.P.C.

- Primary Subcontractors: Contract No.1 — North Country Contractors, LLC, Contract No.2 – Marcellus Construction Co., Inc., Contract No.3A — Joseph J. Lane Construction, Inc.; Contract No.3B – S.C. Spencer Electric, Inc. 

- Financing Source: USDA Rural Development CDBG Small Cities Grant EFC — CWSRF

 

 

BEARDSLEY DESIGN ASSOCIATES

 

Combat Aviation Brigade Storage and Maintenance Hangar

- Project Location: Fort Drum

- Total Construction Cost: $26.8 million

- Approximate Square Footage: 85,500

- Start Date: June 27, 2013

- Completion Date: June 27, 2015

- Building Owner: U.S. Army Corps of Engineers

- Construction Manager: Vetco Contracting Services, LLC

- Architect: Beardsley Design Associates

- Engineer: Beardsley Design Associates

- Landscape Architect: Beardsley Design Associates

- General Contractor: Vetco Contracting Services, LLC

- Primary Subcontractors: Jeffords Steel and Engineering Co., Purcell Construction Corp., Lawman Heating & Cooling, Inc.

- Financing Source: U.S. Department of Defense

 

 

BERNIER, CARR & ASSOCIATES

 

Mexico Academy & Central School Capital Project Phase 3

- Project Location: Mexico Middle School, Mexico, NY

- Total Construction Cost: $12 million

- Building Owner: Mexico Academy & CSD

- Construction Manager: Bernier, Carr & Associates

- Architect: Bernier, Carr & Associates

- Engineer: Bernier, Carr & Associates

- Financing Source: New York State Education Department

 

 

BETTE & CRING, LLC

 

GUSC Energy Biomass CHP Plant

- Project Location: Rome

- Total Construction Cost: $16.4 million

- Approximate Square Footage: 15,000

- Building Owner: GUSC Energy

- Construction Manager: Cogen Power Technologies

- Architect: CHA

- Engineer: CHA

- General Contractor: Bette & Cring, LLC

- Primary Subcontractors: HJ Brandeles Corp.; O’Connell Electric Co., Inc.; Madonia Electric, Inc.; Wellons Boiler Systems

- Financing Source: Oneida Savings Bank

 

Onondaga Community College Multi-Field Complex

- Project Location: Onondaga

- Total Construction Volume: $5.6 million

- Approximate Acreage: 9 acres

- Building Owner: Onondaga Community College

- Architect: King + King Architects

- Engineer: Appel Osborne Landscape Architecture

- Landscape Architect: Appel Osborne Landscape Architecture

- General Contractor: Bette & Cring, LLC

- Primary Subcontractors: Cunningham Excavation Inc., Chenango Contracting Inc., Lysander Construction

- Financing Source: Onondaga County

 

 

CBD CONSTRUCTION, LLC

 

Waterloo Rite Aid

- Project Location: 1929 US Route 20, Waterloo

- Total Construction Cost: $1.9 million

- Approximate Square Footage: 15,000

- Start Date: Jan. 1, 2013

- Completion Date: April 30, 2013

- Building Owner: Rite Aid

- Construction Manager: Ellicott Development Co.

- Architect: Palmisano Architects

- Engineer: BL Companies

- General Contractor: CBD Construction

- Primary Subcontractors: Ron Wright Inc.; C&D Laface Construction; Cornerstone Paving; Padula Roofing; Marzullo Electric; Angelo Chiodo Heating & Air Conditioning; The Effect Group

 

CNY Women’s Health Care Center

- Project Location: 5000 Brittonfield Parkway, DeWitt

- Total Construction Volume: $725,000

- Approximate Square Footage: 10,000

- Start Date: Aug. 13, 2013

- Completion Date: Oct. 31, 2013

- Building Owner: Brittonfield Associates

- Construction Manager: CBD Construction, LLC

- Architect: Dalpos Architects, LLC

- General Contractor: CBD Construction, LLC

- Primary Subcontractors: Widewaters HVAC; ATL Plumbing and Mechanical; Fortino Electric; Wood Etc., Inc.; The Effect Group 

 

CHARLES A. GAETANO CONSTRUCTION CORPORATION

 

Hamilton College Theater & Studio Arts Building

- Project Location: Hamilton College, Clinton

- Total Construction Cost: $35 million

- Approximate Square Footage: 81,000 

- Start Date: Aug. 12, 2012

- Building Owner: Hamilton College

- Construction Manager: Charles A. Gaetano Construction Corp.

- Architect: Machado and Silvetti Associates

- Engineer: Altieri Sebor Wieber LLC - Mechanical Eng.

- Landscape Architect: Reed Hilderbrand LLC

- General Contractor: Charles A. Gaetano Construction Corp.

- Primary Subcontractors: H.J. Brandeles — Mechanical; Huen New York, Inc. — Electrical; Fred Burrows Trucking & Excavating, LLC — Site Work 

 

Feldmeier Equipment New Building

- Project Location: Riverside Industrial Park, Little Falls

- Total Construction Volume: $3.7 million

- Approximate Square Footage: 44,000

- Start Date: September 30, 2013

- Completion Date: Feb. 1, 2014

- Building Owner: Feldmeier Equipment, Inc.

- Construction Manager: Charles A. Gaetano Construction, Corp.

- Engineer: Almy & Associates

- Landscape Architect: Alan Swierczek

- General Contractor: Charles A. Gaetano Construction, Corp.

- Primary Subcontractors: Fred Burrows Trucking & Excavating, Superior Plumbing & Heating, Boscar Electric Co., Inc.

 

 

CHIANIS + ANDERSON ARCHITECTS, PLLC

 

Galaxy Brewing Company

- Project Location: Binghamton

- Total Construction Cost: $1.5 million

- Approximate Square Footage: 9,000

- Start Date: Nov. 15, 2012

- Completion Date: July 15, 2013

- Building Owner: Mike Weisel

- Construction Manager: Construction Group

- Architect: Chianis + Anderson Architects, PLLC

- Engineer: Engineered Solutions

- General Contractor: Construction Group

- Primary Subcontractors: Matco Electric; Petcosky & Sons-Plumbing; Air Temp-Mechanical; Hoffman Construction-Carpentry

 

Professional Home Care

- Project Location: Johnson City

- Total Construction Volume: $4.7 million

- Approximate Square Footage: 33,000

- Start Date: Sept. 1, 2013

- Completion Date: March 1, 2014

- Building Owner: United Health Services Hospitals

- Construction Manager: LeChase Construction Services

- Architect: Chianis + Anderson Architects, PLLC

- Engineer: MH Professional Engineering, Engineered Solutions, Hulbert Engineering and Land Surveying, Klepper, Hahn & Hyatt

- Primary Subcontractors: Krista Construction; Picciano and Sons; Matco Electric; ZMK Construction

 

 

DALPOS ARCHITECTS & INTEGRATORS

 

Creekwalk Commons

- Project Location: Downtown Syracuse — Water Street at Franklin Street

- Approximate Square Footage: 130,000

- Building Owner: Syracuse Creekwalk Commons, Inc.

- Construction Manager: Hueber-Breuer

- Architect: Dalpos Architects & Integrators

- Engineer: Palucci Engineering (Structural); Integrated Design (MEP)

- Landscape Architect: Keplinger-Freeman Associates

- General Contractor: Hueber-Breuer

 

Aloft Hotel

- Project Location: Syracuse Inner Harbor

- Approximate Square Footage: 74,800

- Building Owner: COR Development

- Construction Manager: COR Development

- Architect: Dalpos Architects & Integrators

- Engineer: John P. Stopen Engineering (Structural); Sack Associates (MEP)

- Landscape Architect: C&S Engineers

- General Contractor: COR Development

 

G.M. CRISALLI & ASSOCIATES, INC.

 

Building B-Ithaca

- Project Location: 2430 Triphammer Road, Ithaca

- Total Construction Cost: $1.2 million

- Approximate Square Footage: 8,147

- Start Date: March 4, 2013

- Completion Date: Sept. 1, 2013

- Building Owner: Timemon Holding Company, Ithaca

- Architect: Jagat Sharma Architects, Ithaca

- General Contractor: G.M. Crisalli & Associates, Inc.

 

DestinyUSA New Retail Stores

- Project Location: Destiny USA, 9090 DestinyUSA Drive, Syracuse

- Total Construction Volume: $1.5 million

- Approximate Square Footage: Varied from 1,634 to 24,745 square feet

- Start Date: Jan. 6, 2013

- Completion Date: Feb. 15, 2014

- Building Owner: Various

- Architect: Saks - QPK-Syracuse/ Boston Market — Dalpos, Syracuse/ 5 Witts - Bergman Assoc./ Todds - Nathan Lee Colkitt Arch./  L’Occitane - Kenneth Parks Architects

- General Contractor: G.M. Crisalli & Associates, Inc. 

 

GRANGER CONSTRUCTION COMPANY, INC.

 

Bass Pro Shops Store

- Project Location: Utica

- Approximate Square Footage: 55,000

- Building Owner: Bass Pro Shops

- Construction Manager: Granger Construction Company, Inc.

- Architect: Benchmark Group

- General Contractor: Granger Construction Company, Inc.

 

Hannaford Foods

- Project Location: New Hartford

- Approximate Square Footage: 65,000

- Building Owner: Hannaford Foods

- Construction Manager: Hannaford Foods

- Architect: CS Architects

- General Contractor: Granger Construction Company, Inc.

 

GYMO ARCHITECTURE, ENGINEERING & LAND SURVEYING P.C.

 

Northern Credit Union

- Project Location: NYS Route 11,Town of LeRay at Fort Drum Main Gate

- Total Construction Cost: $2.3 million

- Approximate Square Footage: 3,200

- Start Date: Oct. 1, 2013

- Completion Date: April 1, 2014

- Building Owner: Northern Credit Union

- Construction Manager: GYMO, P.C. Construction Services

- Architect: GYMO Architecture, Engineering & Land Surveying P.C.

- Engineer: GYMO Architecture, Engineering & Land Surveying P.C.

- General Contractor: Hueber-Breuer Construction Co.

- Primary Subcontractors: RSI Roofing, Marzano Paving, Northern Glass, Cota Flooring, STAT Communications

 

Woolworth Building Apartments

- Project Location: Downtown Watertown

- Total Construction Volume: $12.5 million

- Approximate Square Footage: 50,000

- Start Date: Nov. 1, 2013

- Completion Date: June 1, 2015

- Building Owner: White Birch Enterprises

- Construction Manager: Purcell Construction

- Architect: Crawford

- Engineer: GYMO Engineering, Environmental & Construction Services

- General Contractor: Purcell Construction

- Primary Subcontractors: Op-Tech Environmental Services

 

 

THE HAYNER HOYT CORP.

 

Byrne Dairy-Cortlandville Yoghurt & Cheese Facility

- Project Location: Cortlandville

- Approximate Square Footage: 72,000

- Start Date: Aug. 1, 2013

- Completion Date: March 15, 2014

- Building Owner: Byrne Dairy

- Construction Manager: Hayner Hoyt

- Architect: MSKTD & Associates

- Engineer: MSKTD & Associates

- Landscape Architect: QPK Design

- General Contractor: Hayner Hoyt 

- Primary Subcontractors: Huen Electric, Woodcock and Armani, abj Fire Protection, JPW Structural Contracting, Orchard Earth and Pipe, Integrated Industrial Services, Doyner Masonry, Oldcastle Precast, Burns Brothers Concrete, Apple Roofing

- Financing Source: M&T

 

Syracuse University Football Practice Facility

- Project Location: Colvin Street, Syracuse

- Approximate Square Footage: 90,000

- Building Owner: Syracuse University

- Construction Manager: The Hayner Hoyt Corporation

- Architect: Cannon Design

- Engineer: Cannon Design

- Landscape Architect: CHA

- General Contractor: Hayner Hoyt

- Primary Subcontractors: Ballard Construction, Allied Electric, abj Fire Protection, Hayward Baker, Jon T. Rich Construction, American Buildings, Markim Erectors, Doyner Masonry

 

 

HOLMES-KING-KALLQUIST & ASSOCIATES, ARCHITECTS, LLP

 

VanKeuren Square; Homeless Veterans Housing

- Project Location: Syracuse

- Total Construction Cost: $8.1 million

- Approximate Square Footage: 50,068

- Building Owner: Housing Visions Unlimited

- Architect: Holmes-King-Kallquist & Associates Architects

- Engineer: St. Germain & Aupperle, Structural & GHD, Mechanical & Electrical

- Landscape Architect: Appel Osborne Landscape Architecture

- General Contractor: Housing Visions Construction Co., Inc.

- Financing Source: New York State Division of Housing and Community Renewal Housing, NYS Housing Trust Fund Corporation, Homeless Housing and Assistance Corporation, City of Syracuse, Enterprise Community Investment, Inc., Save the Rain, NYSERDA, Home Depot 

 

Bright House Networks

- Project Location: DeWitt

- Approximate Square Footage: 23,500

- Building Owner: Reit Management; Tenant: Bright House Networks

- Architect: Holmes-King-Kallquist & Associates Architects

- Engineer: Sack & Associates

- General Contractor: Rich and Gardner

 

 

HOLT ARCHITECTS, P.C.

 

Natural Science Center

- Project Location: Binghamton

- Total Construction Cost: $21 million

- Approximate Square Footage: 48,700

- Building Owner: SUNY Broome

- Construction Manager: LeChase Construction Services

- Architect: HOLT Architects, PC

- Engineer: Erdman Anthony (MEP), Ryan-Biggs Associates (Structural), Shumaker Engineering & Surveying (Civil)

- Landscape Architect: Trowbridge Wolf Michaels Landscape Architects

- General Contractor: Fahs Construction Group (Construction), Piccirilli-Slavik & Vincent Plumbing & Heating, Inc. (Mechanical), Schuler-Haas Electric Corp. (Electrical)

- Financing Source: Broome County

 

Surgical Services Addition & Renovation 

- Project Location: Ithaca

- Total Construction Volume: $11 million

- Approximate Square Footage: 29,400

- Building Owner: Cayuga Medical Center in Ithaca

- Construction Manager: LPCiminelli

- Architect: HOLT Architects, PC

- Engineer: Sack & Associates (MEP), Ryan-Biggs Associates (Structural), TG Miller (Civil)

- Landscape Architect: Trowbridge Wolf Michaels Landscape Architects

- Primary Subcontractors: HMI Mechanical Systems (Mechanical & Plumbing), Richardson Brothers Electrical (Electrical), Rochester Rigging & Erectors (Structural), McPherson Builders (Concrete), Edger Enterprise (Site Work), Traver Construction (Precast & Masonry), Edward Schalk & Son (Gypsum Board & Ceilings)

 

 

HUEBER-BREUER CONSTRUCTION CO., INC.

 

Syracuse Hancock Airport Passenger Terminal Security Access Improvement

- Project Location: Syracuse

- Total Construction Cost: $60 million

- Approximate Square Footage: 147,000

- Building Owner: City of Syracuse

- Construction Manager: C & S Companies

- Architect: C & S Companies

- Engineer: C & S Companies

- General Contractor: Hueber-Breuer Construction Co., Inc.

- Primary Subcontractors: Burns Bros., O’Connell Electric, Edward Schalk & Son

- Financing Source: Passenger Facility Charge (PFC) TSA grant

 

Onondaga Community College Academic II

- Project Location: Syracuse

- Total Construction Volume: $13.5 million

- Approximate Square Footage: 45,000

- Building Owner: Onondaga Community College

- Construction Manager: C & S Companies

- Architect: Cannon Design

- Engineer: C & S Companies

- Landscape Architect: Cannon Design

- General Contractor: Hueber-Breuer Construction Co., Inc.

- Primary Subcontractors: Raulli & Sons, Ajay Glass General Interiors

- Financing Source: Onondaga County and New York State

 

 

KLEPPER, HAHN & HYATT

 

Sadler Hall Dining Expansion & Renovation

- Project Location: 1000 Irving Ave., Syracuse

- Total Construction Cost: $4.2 million

- Approximate Square Footage: 4,900

- Start Date: Oct. 15, 2011

- Completion Date: Aug. 1, 2013

- Building Owner: Syracuse University

- Architect: Ashley McGraw Architects

- Engineer: Klepper, Hahn & Hyatt

- General Contractor: The Hayner-Hoyt Corporation

- Primary Subcontractors: CME Associates, Saunders Concrete, KBI Concrete Construction

 

LECHASE CONSTRUCTION SERVICES, LLC

 

Price Chopper

- Project Location: Alexandria Bay

- Total Construction Cost: $4 million

- Approximate Square Footage: 32,800

- Start Date: Nov. 15, 2012

- Completion Date: May 15, 2013

- Building Owner: Golub Corp.

- Construction Manager: LeChase Construction Services, LLC

- Architect: Cuhaci & Peterson

- Engineer: Cuhaci & Peterson

- Landscape Architect: Redstone

- General Contractor: LeChase Construction Services, LLC

- Primary Subcontractors: Cunningham Excavation (Site Work), Ron Wright (Framing & Interior Finishes), Superior Steel (Structural/Misc. Steel), Woodcock and Armani (Plumbing), Demco Electric (Electrical)

- Financing Source: Golub Corp.

 

Binghamton University — Center of Excellence Phase II

- Project Location: Vestal

- Total Construction Volume: $11 million

- Approximate Square Footage: 114,000

- Building Owner: Binghamton University

- Construction Manager: Binghamton University

- Architect: Binghamton University

- Engineer: Stantec

- Landscape Architect: Binghamton University

- General Contractor: LeChase Construction Services, LLC

- Primary Subcontractors: PS&V (Plumbing), J&K Plumbing & Heating (HVAC), Schuler Haas (Electrical), Ajay Glass & Glazing (Curtain Wall & Glass).

- Financing Source: State University Construction Fund

 

 

LEND LEASE (US) CONSTRUCTION INC.

 

Owego-Apalachin CSD — New Elementary School

- Project Location: Owego

- Total Construction Cost: $72 million

- Approximate Square Footage: 124,000

- Start Date: Dec. 1, 2013

- Completion Date: Aug. 31, 2015

- Building Owner: Owego-Apalachin CSD

- Construction Manager: Lend Lease (US) Construction Inc.

- Architect: Highland Associates

- Engineer: Highland Associates

- General Contractor: TBD

- Primary Subcontractors: TBD

- Financing Source: School bonds

 

 

NATIONAL STRUCTURES, INC.

 

TJ Maxx in the Johnstown Shopping Center

- Project Location: North Comrie Ave., Johnstown

- Total Construction Cost: $2 million

- Approximate Square Footage: 24,000

- Start Date: Aug. 13, 2013

- Completion Date: Feb. 14, 2014

- Building Owner: Wachs Johnstown Associates, LLC

- Construction Manager: Dominick Madia

- Architect: Harrington & Mosher, Architects, P.C

- Engineer: Hogan Engineering, P.C.

- General Contractor: National Structures Inc.

- Primary Subcontractors: Direct HVAC Services, Inc., Ed Carr Electric, Ward Steel Co., Inc.

- Financing Source: First Niagara

 

”Herb” Philipson’s

- Project Location: Arcadia Shopping Center, Route 31 East, Newark

- Total Construction Volume: $1.4 million

- Approximate Square Footage: 48,000

- Building Owner: Wachs Newark Development, LLC

- Construction Manager: Dominick Madia

- Architect: Harrington & Mosher, Architects, P.C

- Engineer: Hogan Engineering, P.C.

- General Contractor: National Structures Inc.

- Primary Subcontractors: Direct HVAC Services, Inc., Gerula Electric, Inc., Pro Plumbing, Inc.

- Financing Source: Self-financed by owner

nelson associates

architectural 

engineering

 

Meadowbrook Terrace Assisted Living Complex

- Project Location: Carthage

- Total Construction Cost: $7.9 million

- Approximate Square Footage: 43,000 

- Start Date: Nov. 1, 2011

- Completion Date: Dec. 1, 2013

- Building Owner: Carthage Area Hospital

- Construction Manager: Nelson Associates Architectural Engineering

- Architect: Nelson Associates Architectural Engineering

- Engineer: Nelson Associates Architectural Engineering

- General Contractor: Murnane Construction

- Primary Subcontractors: Primes — Plumbing and Fire Protection: Norwood Plumbing; HVAC: Tag Mechanical; Electric and Fire Alarm: S & L Electric

- Financing Source: Multiple sources including a HEAL NY Phase 20 Alternative Long Term Care Initiative grant

 

 

OLIVA CONSTRUCTION COMPANY

 

Old Collamer Road Corporate Center

- Project Location: 6800 Old Collamer Road, DeWitt

- Total Construction Cost: $2.2 million

- Approximate Square Footage: 25,000

- Completion Date: Jan. 1, 2014

- Building Owner: Oliva Management, LLC

- Construction Manager: Oliva Construction Company

- Architect: JS Hagan Architect, PC

- Engineer: Dunn & Sgromo Engineers, PLLC

- General Contractor: Oliva Construction Co.

 

 

PARSONS-MCKENNA CONSTRUCTION CO., INC.

 

Bankers Healthcare Group

- Project Location: 110 Solar St., Syracuse

- Total Construction Cost: $3.1 million

- Approximate Square Footage: 20,000

- Completion Date: July 20, 2014

- Building Owner: Bankers Healthcare Group

- Architect: Harmony Design Associates

- Engineer: Jeremy Fudo

- Landscape Architect: EDR, Inc

- General Contractor: Parsons-McKenna Construction Co., Inc

- Primary Subcontractors: Remlap Construction, JPW Steel Erectors, Fortino & Son Electric, Top Flight Heating, Inc, Green Plumbing, Associated Fire Protection, Bon-Ton Glass, TCM Flooring, Berg Painting, Sterling Creek Roofing

 

 

THE PIKE COMPANIES, LTD

 

Cornell University Stocking Hall

- Project Location: Ithaca

- Total Construction Cost: $70 million

- Approximate Square Footage: 180,000

- Start Date: Nov. 1, 2010

- Completion Date: Feb. 28, 2015

- Building Owner: Cornell University

- Construction Manager: Gilbane Building Company

- Architect: Mitchell/Giurgola Architects

- Engineer: M/E Engineering, WebberSmith

- Landscape Architect: Dirtworks PLC 

- General Contractor: The Pike Company

- Primary Subcontractors: Matco Electric; EW Tompkins 

- Financing Source: State University Construction Fund

 

SUNY Upstate Medical University Cancer Center Expansion

- Project Location: Syracuse

- Total Construction Volume: $70 million

- Approximate Square Footage: 146,000 square feet

- Start Date: April 1, 2012

- Completion Date: July 31, 2014

- Building Owner: SUNY Upstate Medical University

- Construction Manager: LeChase Construction Services

- Architect: Ewing Cole Architects, Engineers, Interior Designers & Planners

- Engineer: Ewing Cole Architects, Engineers, Interior Designers & Planners

- General Contractor: The Pike Company

- Primary Subcontractors: Heuber-Breuer, Buffalo Structural, Thyssen-Krupp Elevator, A.C. Dellovade, Elmer W. Davis, North Central Mechanical, and Matco Electric

 

 

PLUMLEY ENGINEERING, P.C.

 

McLane Northeast Expansion

- Project Location: Town of Lysander, Onondaga County

- Approximate Square Footage: 90,000 square feet of building additions

- Building Owner: McLane Northeast

- Construction Manager: Construction Management Technology

- Architect: Elements of Architecture, Inc.

- Engineer: Plumley Engineering, P.C.

- General Contractor: Construction Management Technology

- Primary Subcontractor: Site: Lan-Co Companies, Inc.

 

 

QPK DESIGN, LLP — ARCHITECTURAL ENGINEERING SITE & PLANNING

 

Empower FCU — Corporate Headquarters Rehabilitation

- Project Location: Salina

- Approximate Square Footage: About 75,000

- Building Owner: Empower Federal Credit Union

- Construction Manager: Hayner Hoyt Corp.

- Architect: QPK Design, LLP - Architecture Engineering Site & Planning

- Engineer: Sack & Associates Consulting Engineers

- Landscape Architect: QPK Design

- Primary Subcontractors: John P. Stopen Engineering, LLP

 

College Suites at City Station East

- Project Location: Troy

- Total Construction Volume: $9.3 million

- Approximate Square Footage: 95,000

- Building Owner: City Station East, LLC

- Architect: QPK Design, LLP - Architecture Engineering Site & Planning

- Engineer: CW Engineering

- Landscape Architect: QPK Design, LLP - Architecture Engineering Site & Planning

- General Contractor: BBL Construction Services, LLC

- Primary Subcontractors: Stroud, Pence & Associates, LTD — Structural Engineering; Hershberg & Hershberg — Civil Engineering

 

 

ROBERTSON STRONG APGAR ARCHITECTS, P.C.

 

Dr. Weeks Elementary School-Syracuse City School District

- Project Location: 710 Hawley Ave., Syracuse 

- Total Construction Cost: $18 million

- Approximate Square Footage: 108,000

- Start Date: Sept. 30, 2011

- Completion Date: Jan. 2013

- Building Owner: Syracuse City School District 

- Construction Manager: Gilbane Building Co.

- Architect: Robertson Strong Apgar Architects

- Engineer: Watts Engineers

- Landscape Architect: Landscape and Prospect

- General Contractor: Fahs Construction Group

- Financing Source: New York state

 

Northwest Area YMCA

- Project Location: Lysander

- Total Construction Volume: $17 million

- Approximate Square Footage: 100,000

- Start Date: Nov. 2013

- Completion Date: TBD

- Building Owner: YMCA of Greater Syracuse 

- Construction Manager: Heuber-Bruer Construction Co., Inc.

- Architect: Robertson Strong Apgar Architects

- Engineer: Paul Sack & Associates, IE Engineering 

- Landscape Architect: Clough Harbor and Associates 

 

 

RYAN-BIGGS ASSOCIATES, P.C.

 

Breckenridge Place

- Project Location: Ithaca

- Total Construction Cost: $14 million

- Approximate Square Footage: 55,300

- Start Date: July 1, 2012

- Completion Date: Dec. 20, 2013

- Building Owner: Ithaca Neighborhood Housing Services

- Construction Manager: Christa Construction, LLC

- Architect: HOLT Architects, P.C.

- Engineer: Ryan-Biggs Associates, P.C.

- Landscape Architect: Trowbridge Wolf Michaels Landscape Architects, LLP

- General Contractor: Christa Construction, LLC

- Primary Subcontractors: CME Associates, Inc. (Testing Lab); Dave Traver Masonry; W.F. Saunders & Sons; Hertel Steel 

- Financing Source: The City of Ithaca’s Home Investment Partnerships (HOMES) Program; the Ithaca Urban Renewal Agency; the Tompkins County Community Housing Trust; the New York State Housing Trust Fund Corporation; NeighborWorks America; and the Federal Home Loan Bank of New York, through the Tompkins Trust Company. (Information from ithacanhs.org)

 

 

SACK & ASSOCIATES CONSULTING ENGINEERS, PLLC

 

Village of Skaneateles Renovation of Former Fire Station

- Project Location: 46 E. Genesee St., Skaneateles

- Total Construction Cost: $1.4 million

- Approximate Square Footage: 5,000

- Start Date: May 12, 2013

- Building Owner: Village of Skaneateles

- Architect: QPK Design

- Engineer: Sack & Associates Consulting Engineers, PLLC

- Primary Subcontractors: Knapp Electric/Avolio Brothers LLC/Tag Mechanical

Empower Federal Credit Union — Corporate Headquarters Renovation

- Project Location: Salina

- Total Construction Volume: $7.5 million

- Approximate Square Footage: About 75,000

- Building Owner: Empower Federal Credit Unit

- Construction Manager: The Hayner Hoyt Corporation

- Architect: QPK Design

- Engineer: Sack & Associates Consulting Engineers, PLLC

- Primary Subcontractors: Woodcock & Armani/Phoenix Electric/Century Heating

 

 

SWBR ARCHITECTURE, ENGINEERING & LANDSCAPE ARCHITECTURE, P.C.

 

Rescue Mission Day Center-Shelter

- Project Location: Syracuse

- Total Construction Cost: $5.7 million

- Approximate Square Footage: 35,081 

- Building Owner: Rescue Mission

- Construction Manager: LECESSE Construction 

- Architect: SWBR Architects

- Engineer: SWBR Architects (Structural), Turner Engineering (MEP)

- Landscape Architect: Keplinger Freeman Associates

- Primary Subcontractors: AECC (Abatement Designer)

- Financing Source: HHAP, FHLB, Rescue Mission

 

Rescue Mission Master Plan

- Project Location: Syracuse

- Approximate Square Footage: 152,550 

- Building Owner: Rescue Mission

- Architect: SWBR Architects

- Engineer: SWBR Architects, Turner Engineering

- Landscape Architect: Keplinger Freeman Associates

- General Contractor: LECESSEE Construction

- Financing Source: TBD

 

 

VIP STRUCTURES

 

ITT Goulds Pumps — Project Cobalt

- Project Location: Seneca Falls

- Total Construction Cost: $12 million

- Approximate Square Footage: 90,000

- Start Date: Oct. 1, 2013

- Completion Date: June 1, 2014

- Building Owner: ITT Goulds Pumps

- Construction Manager: VIP Structures, Inc.

- Architect: VIP Architectural Associates

- Engineer: IPD:Engineering

- Landscape Architect: Napierala Consulting 

- General Contractor: VIP Structures, Inc. 

- Primary Subcontractors: Lanco, J&E Electric, Century Mechanical, Burns Brothers, Western Concrete 

 

Vernon Downs

- Project Location: Vernon 

- Total Construction Volume: $8.5 million

- Approximate Square Footage: 100,000

- Start Date: Nov. 1, 2013

- Completion Date: Dec. 31, 2014

- Building Owner: Vernon Downs Casino & Hotel 

- Construction Manager: VIP Structures, Inc. 

- Architect: VIP Architectural Associates

- Engineer: IPD: Engineering 

- Landscape Architect: Maxian + Horst 

- General Contractor: VIP Structures, Inc.

 

 

WALSH AND SONS CONSTRUCTION CORP.

 

Our Lady of Sorrows Church

- Project Location: Vestal

- Total Construction Cost: $2.5 million

- Approximate Square Footage: 20,000

- Start Date: May 1, 2012

- Completion Date: Dec. 22, 2013

- Building Owner: Our Lady of Sorrows Church

- Construction Manager: Walsh & Sons Construction

- Architect: Teitsch-Kent-Fay Architects, P.C.

- Engineer: Delta Engineers, Architects & Land Surveyors, PC

- Landscape Architect: Rick York

- General Contractor: Walsh & Sons Construction

- Primary Subcontractors: Wade Electric, Herzog Plumbing, Suretemp, Petcosky & Son, B&F Glass, RCR Construction, The Gutterman

- Financing Source: Owner-provided

 

St. Vincent Blessed Sacrament Church

- Project Location: Vestal

- Total Construction Volume: $500,000

- Approximate Size: Site Work - 1 acre

- Start Date: Sept. 25, 2012

- Completion Date: June 1, 2013

- Building Owner: St. Vincent Blessed Sacrament

- Construction Manager: Walsh & Sons Construction Corp.

- Landscape Architect: Haas Landscape Architects

- General Contractor: Walsh & Sons Construction Corp.

- Primary Subcontractors: McKnight Custom Concrete, Markoff Concrete

- Financing Source: Owner

 

 

WHELAN & CURRY CONSTRUCTION SERVICES, INC.

 

Plaza of the Arts

- Project Location: 161 Genesee St., Auburn

- Total Construction Cost: $2.8 million

- Approximate Square Footage: 20,000

- Completion Date: May 31, 2014

- Building Owner: WST33 LLC

- Construction Manager: Whelan & Curry Construction Services, Inc.

- Architect: Crissey Architectural, PC

- Engineer: St. Germain & Aupperle Consulting Engineers,LLP

- Landscape Architect: Keplinger Freeman Associates

- Financing Source: Cayuga County IDA

Patterson Warehousing

- Project Location: Fulton 

- Total Construction Volume: $800,000

- Approximate Square Footage: 22,000 

- Building Owner: Will Patterson III 

- Construction Manager: Whelan & Curry Construction Services, Inc.

- Engineer: St. Germain & Aupperle Consulting Engineers, LLP

- Financing Source: County of Oswego IDA

 

 